Question No. 1

 

Alpha Company is a software house currently working on a project of Hotel management system. Alpha Company has to complete this project in 30 days. Draw the Task network diagram for Alpha Company to complete this project, the information about each task is given below:

 

 

Name of Task

Description of Task

Duration in days

Immediate Predecessor

  1.  

Requirement Specification

4

-

  1.  

Design

6

A

  1.  

Code

10

B

  1.  

Test

6

C

  1.  

Document

4

D, C

 

 

 

Question No. 2

 

Quality Soft is a software house currently working on a project of stock management system. For this project they have calculated the Cost performance index (CPI) = 0.9, the Actual cost work performed (ACWP) is 550. You are required to find the Budgeted Cost of Work Perform (BCWP).

 

Provide your answer in the following table:

 

 

Calculation

Result

 

 

 

 

 

 

 

 

 

 

Share This With Friends......


How to Find Your Subject Study Group & Join.

Find Your Subject Study Group & Join.

+ Click Here To Join also Our facebook study Group.


This Content Originally Published by a member of VU Students.

+ Prohibited Content On Site + Report a violation + Report an Issue


Views: 5363

See Your Saved Posts Timeline

Attachments:

Replies to This Discussion

CPI=BCWP/ACWP

0.9=BCWP/550

0.9*550=BCWP

BCWP=495

is it ok??

yes

NOPE
=445.5

how it is 445.5, did you point out something plss share

just simplification 

ur ans is wrong...
correct ans is 495=BCWP

thanks 

for ist question understand this table

I got the Q's no 2 but i didn't get the idea of Q no 1... Q#1 main kerna kiya hai..

Q2 ka ans bata dain please

tHE ANSWER IS 495!! 

RSS

Forum Categorizes

Job's & Careers (Latest Jobs)

Admissions (Latest Admissons)

Scholarship (Latest Scholarships)

Internship (Latest Internships)

VU Study

Other Universities/Colleges/Schools Help

    ::::::::::: More Categorizes :::::::::::

Member of The Month

© 2017   Created by + M.Tariq Malik.   Powered by

Promote Us  |  Report an Issue  |  Privacy Policy  |  Terms of Service