CS611 Software Quality Engineering Assignment No 02 Spring 2019 Solution & Discussion
Tags:
The following formulas will be used for the following examples.
PV = Planned Completion (%) * BAC
EV = Actual Completion (%) * BAC
CPI = EV/AC
SPI = EV/PV
Suppose you have a budgeted cost of a project at $900,000. The project is to be completed in 9 months. After a month, you have completed 10 percent of the project at a total expense of $100,000. The planned completion should have been 15 percent.
Now, let’s see how healthy the project is by computing the CPI and SPI.
From the scenario, you can extract the following:
The Planned Value (PV) and Earned Value (EV) can then be computed as follows:
Compute the earned value variances:
Interpretation: Since both Cost Performance Index (CPI index) and Schedule Performance Index (SPI index) are less than 1, it means that the project is over budget and behind schedule. This example project is in major trouble and corrective action needs to be taken. Risks management needs to kick-in.
Suppose you are managing a software development project. The project is expected to be completed in 8 months at a cost of $10,000 per month. After 2 months, you realize that the project is 30 percent completed at a cost of $40,000. You need to determine whether the project is on-time and on-budget after 2 months.
Step 1: Calculate the Planned Value (PV) and Earned Value (EV)
From the scenario,
Therefore,
Step 2: Compute the Cost Performance Index (CPI) and Schedule Performance Index (SPI)
In dono example me Actual cost question me hi dedi gai hai.
Assignment k question me actual cost nahi di gai
nabeel ur right ya AC dia he ni tu find kasy karian gay
ji han lekin ab humny kar liya hai find Jazak Allah Khair. Eid Mubarak
Question # 02
Answer
EV = 150000 * 15 / 100 = 22500
PV = 150000 * 20 / 100 = 30000
AC = 150000 * 15 / 100 = 22500
Note AC and EV are same
SPI = EV / PV = 22500 / 30000 = 0.75 If the SPI is less than 1, it means the project is behind schedule.Handouts page # 41
CPI = EV / AC = 22500 / 22500 = 1 If the CPI is equal to 1, it means the project is as per the planned budget. Handouts page # 41
Note: This is idea solution
Asslam u Alikum.Koi Allah ka bnda ya bndi solution share kr de plzzz
Nabeel bhae ye solution done h?
ji done hai lekin yeh idea hai baki aap net par search karen "if actual value and earned value same"
koi complate he solution send kar do
SPI = EV / PV = 22,500 / 30,000 = 1.333
Hnadouts page # 41
If the SPI is greater than 1, it means the project is ahead of schedule.
CPI = EV / AC = 22,500 / 22,500 = 0
Hnadouts page # 41
If the CPI is less than 1, it means the project is over budget.
ye dono answer wrong lag ry ha han. use calculator and see?
Thank you for comment me dubara dekhta hun
© 2021 Created by + M.Tariq Malik.
Powered by
Promote Us | Report an Issue | Privacy Policy | Terms of Service
We non-commercial site working hard since 2009 to facilitate learning Read More. We can't keep up without your support. Donate.
We are user-generated contents & non-commercial site. All product, videos, pictures & others contents on site don't seem to be beneath our Copyrights & belong to their respected owners & freely available on public domains. All Contents on site are for personal & non-commercial use.We believe in Our Policy & do according to them. If Any content is offensive in your Copyrights then please email at m.tariqmalik@gmail.com with copyright detail & We will happy to remove it immediately.
Management: Admins ::: Moderators
Awards Badges List | Moderators Group
All Members | Featured Members | Top Reputation Members | Angels Members | Intellectual Members | Criteria for Selection
Become a Team Member | Safety Guidelines for New | Site FAQ & Rules | Safety Matters | Online Safety | Rules For Blog Post