CS611 Software Quality Engineering Assignment No 02 Spring 2019 Solution & Discussion

Views: 932

Replies to This Discussion

btao bhai kouch thek ha k ni?

Answer is  0.75

New wala answer check kar k batain! THX

Question # 02
Answer
EV = 150000 * 15 / 100 = 22500
PV = 150000 * 20 / 100 = 30000
AC = 150000 * 15 / 100 = 22500
Note AC and EV are same
SPI = EV / PV = 22500 / 30000 = 0.75 If the SPI is less than 1, it means the project is behind schedule.Handouts page # 41  

CPI = EV / AC = 22500 / 22500 = 1 If the CPI is equal to 1, it means the project is as per the planned budget. Handouts page # 41  
Note: This is idea solution

1st question send kro thek wla or ye b check jaldi

kro. https://www.pakeducation4u.com/cs-611-assignment-2-solution-spring-...

meny bhi yehi chose kiya hai

Direct
Direct
Direct
Indirect
Indirect

yeh lo change kar lo es main fil hall ye assignemnt tahke hn 

EID mubarak ho All friend

Attachments:

Is me value wrong put hui wi hain formula me. THX Eid Mubarak

RSS