ASSIGNMENT QUESTION:
Alec Ltd. is one of the largest electronic equipment producers in the country. It
undertakes the work according to the consumer tastes and preferences. Following data is
for the December 2012.
Cost from department - 1 Rs. 10,000
Cost added in department - 2:
Material Rs. 40,000
Labor Rs. 50,400
FOH Rs. 67,200
The quantity schedule shows that 20,000 units were received during the month from the
department - 1 and 12,000 units transferred to finished goods storeroom. 8,000 units in
process were 100% complete as to material and 60 % complete as to the conversion cost.
By using the above information, you are required to prepare/calculate:
1. Quantity schedule. 02 Marks
2. Cost accumulated in the department. 06 Marks
3. Accounting treatment / Cost apportionment. 09 Marks
4. Equivalent production units for material & conversion cost. 03 Marks
5. Per unit cost. 07 Marks
(NOTE: 03 MARKS FOR GOOD FORMATTING AND PRESENTATION)

Views: 3388

Attachments:

Replies to This Discussion

cost per unit is 9.5 not 9

Alec Ltd.

Cost of Production Report.

For the Month of December 2012

I-Quantity Schedule:

            Units received previous dept #                                                               20,000

            Unites completed and transfer out                 12,000

            Unites still in process                                       8,000

                                                                                                                            20,000

II-Cost Accumulated in the Department / Process:

             Cost received from preceding department is                                      Rs.10, 000

            Cost added by department-11:

            Direct Material                                               Rs. 40,000

            Direct Labor                                                    Rs. 50,400     

            Factory overhead                                             Rs. 67,200               Rs. 1, 57,600

                                                                                                                     Rs. 1, 67,600    

III-Calculation of Equivalent Units Production:

            (100% of completed units + % of units in process)  + Previous department units 

            Direct Material                        (12,000x100%)+(8,000x100%)        = 20,000 Units

            Direct Labor                              (12,000x100%)+(8,000x60%)        = 16,800 Units

            F.O.H                                         (12,000x100%)+(8,000x60%)        =16,800 Units

IV- Unit Cost:

            Previous department = Total cost /Number of units = 10,000 / 20,000 = Rs. 0.50

           

            Direct Material                                        40,000/ 20,000 = 2.00

            Direct Labor                                            50,400 /16,800 = 3.00

            F.O.H                                                       67,200 / 16,800 = 4.00

                                                                                                                        Rs. 9.00

 Rs. 9.50

 

 

V- Apportionment of the Accumulated Cost to Finished Goods:

            Cost of units transferred to the next department

            No of completed units x Total cost per unit:

                        12,000         x         9.50                                        = 1, 14,000

            Units in process:

            Cost of preceding department (8,000 x 0.5)              =        Rs. 4,000

            Direct Material           (8,000x100%) x 2.00              =        Rs. 16,000

            Direct Labor       (8,000x60%) x 3.00                                    =       Rs. 14,400

            F.O.H              (8,000x60%) x 4.00                            =       Rs. 19,200                     

                                                                                                                53,600

                                                                                                      Rs. 1, 67,600

 

_____________________________________________________________________

 

2no mein sy kn sa thk solution hy???????????????????

Dono he theak hain dear bs calulation kar lana tori. Zahid Hayat wala bikul theak hai

g  zahid hayat wala solution bilkul theak hai

Becoz zahid hayat nay bilkul book walay method sy kiya hai

thanks to all....................

RSS

Looking For Something? Search Below

Latest Activity

Sophie posted a discussion
5 hours ago
⭐ "Mannat"⭐✔️ liked Black Bird Scientist's discussion graphic designer required
5 hours ago
+ ! zεε liked иαвєєℓ αнмє∂'s discussion CS619 Project Students
10 hours ago
Hamid left a comment for jiya ali
11 hours ago
Hamid and jiya ali are now friends
11 hours ago
Usama shahid joined + M.Tariq Malik's group
18 hours ago
Profile Iconsria aslam, Khawir Abbas and Sana Shafaq joined Virtual University of Pakistan
22 hours ago
Abdul Rehman updated their profile
Saturday

VIP Member Badge & Others

How to Get This Badge at Your Profile DP

------------------------------------

Management: Admins ::: Moderators

Other Awards Badges List Moderators Group

© 2021   Created by + M.Tariq Malik.   Powered by

Promote Us  |  Report an Issue  |  Privacy Policy  |  Terms of Service