Assignment No. 02
Semester: Spring 2020

CS615 Software Project Management

 

Total Marks: 11

 

Due Date: 11-June-20

 

Assignment no. 2 covers Lec#7 to Lec#12.

 

 

Objectives of Assignment:

 

  • You will learn the project and its management activities.

 

 

Uploading instructions:

 

  • Your assignment must be in .doc format.(Any other formats like scan images, PDF, Zip, rar, bmp, docx etc will not be accepted).
  • No assignment will be accepted through email.

 

 

Rules for Marking:

 

It should be clear that your assignment will not get any credit if:

 

·         The assignment is submitted after due date.

·         The submitted assignment does not open or file is corrupted.

·         Your assignment is copied from internet, handouts or from any other student

      (Strict disciplinary action will be taken in this case).

 

 

Assignment

 

 

Question No 1:

 

Many software project managers learn about the so-called management skills and concepts that are actually myths. You are required to differentiate the myth and reality and write in the below table.


Note: Reality must be written against true and relevant myth. Follow given pattern to answer in the below answer sheet (table). Answer in any other format than below answer sheet will get zero marks.

 

A.    Available resource either best or worst. Make project successful in a combined effort.

B.     A general statement of objectives is sufficient to begin work on the software project.

C.    Appointment of more (extra) resources to complete project according to the given schedule.

D.    Software applications are very much flexible, so stakeholder (client) or project manager can change software project requirements at any phase of the development.

E.     Implementing client-server architecture or web enabling an application considered to run software projects smoothly.

F.     When combined the best and worst resources, this drags down the productivity and efficiency of the software project. Moreover, it increases the completion time.

G.    It is must to ensure that information about interface constraints, functions, assumptions, performance and validation criteria collected by software project manager. Because detailed and formal project description of customer requirements required before start the project.

H.    Appointment of additional resources such as people in a software project development process delayed the project.

I.       Delaying the project completion time, because adding additional resources required time to understand the software requirements, design and standards required for this particular project.

J.      Change in the application’s requirements during the construction phase, actually increases the cost of the project at a high level.

K.    Different application development approaches have unique advantages and disadvantages. So considering a single technology platform, architecture or language as one point solution is not a good idea.

 

Answer Sheet:

                                           

Myth

Reality

Z

X

Y

W

R

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: you are required to watch video lessons and consult handouts to solve this assignment.

 

 

Deadline: Your assignment must be uploaded/submitted on or before 11 June 2020.

 


+ http://bit.ly/vucodes (Link for Assignments, GDBs & Online Quizzes Solution)

+ http://bit.ly/papersvu (Link for Past Papers, Solved MCQs, Short Notes & More)

+ Click Here to Search (Looking For something at vustudents.ning.com?)

+ Click Here To Join (Our facebook study Group)


Views: 170

Attachments:

Replies to This Discussion

CS615 Software Project Management Assignment 2 Solution & Discussion Spring 2020


CS615 Assignment 2 Solution Idea:

 

QUESTION 1: Many software project managers learn about the so called managers’ skills and concepts that are actually myths. You are required to differentiate the myth and reality and write in the below table.

A. Available resource either best or worst. Make project successful in a combined effort.

B. A general statement of objectives is sufficient to begin work on the software project.

C. Appointment of more (extra) resources to complete project according to the given schedule.

D. Software applications are very much flexible, so stakeholder (client) or project manager can change software project requirements at any phase of the development.

E. Implementing client-server architecture or web enabling an application considered to run software projects smoothly.

F. When combined the best and worst resources, this drags down the productivity and efficiency of the software project. Moreover, it increases the completion time.

G. It is must to ensure that information about interface constraints, functions, assumptions, performance and validation criteria collected by software project manager. Because detailed and formal project description of customer requirements required before start the project.

H. Appointment of additional resources such as people in a software project development process delayed the project.

I. Delaying the project completion time, because adding additional resources required time to understand the software requirements, design and standards required for this particular project.

J. Change in the application’s requirements during the construction phase, actually increases the cost of the project at a high level.

K. Different application development approaches have unique advantages and disadvantages. So considering a single technology platform, architecture or language as one point solution is not a good idea.

 

SOLUTION SHEET:

Myth

Reality

A

F

B

G

C

H

I

D

J

F

K

#cs615assignment2 #cs615softwareproject2 #cs615assignment
CS615 Software Project Management | Assignment # 2 | 13 June 2020

#cs615assignment2 #cs615softwareproject2 #cs615assignment #arbabhussain

RSS

Looking For Something? Search Here

HELP SUPPORT

This is a member-supported website. Your contribution is greatly appreciated!

© 2020   Created by +M.Tariq Malik.   Powered by

Promote Us  |  Report an Issue  |  Privacy Policy  |  Terms of Service

.