Here goes my 2nd Quiz.

By Juste

I have only saved the MCQ'S and my answers, didn't saved other options. Verify all answers yourself. Please share your quizzes as well.


====================================

 

In a matrix organization, the project manager is likely to experience:

Conflict and difficulties in team building

Good customer relations

Difficulties in getting the best workers assigned to the project

*All of the given options

 

Which of the following refers to a narrative description of the work to be accomplished?

*The statement of work (SOW)

The project specifications

The milestone schedule

The work breakdown structure (WBS)

 

A Gantt chart is useful in determining __________.

The level of effort for a task

When a task starts and stops

*Which are the critical tasks

Who is assigned to do a task

 

In which of the following approaches, individual work items are estimated and summed up in order to get total estimate?

*Computerized approach

 

“A construction firm can select the best subset of a large group of potential projects on which to bid” is an example of which of the following?

*Project Selection

Project evaluation

Project implementation

Project Execution

 

Which of the following refers to “Planned expenditures required to achieve or exceed objectives”?

Objective

Program

Schedule

*Budget

 

If a model is suggested by a senior and powerful official in the organization, it is called

*Sacred Cow Model

Operating Model

Competitive Model

Compulsive Model

 

All of the following are the goals of project planning EXCEPT:

Develop expertise in a given area

To become competitive

To modify an existing facility for later use

*To prepare work breakdown structure

 

Which of the following is the ability to work with people, making cooperative effort, teamwork, make them feeling secure and free to express their opinions?

Technical Skill

*Human Skill

Conceptual Skill

Design Skill

 

The project manager is responsible for coordinating and integrating activities across multiple functional lines. In order to do so, the project manager needs all of the following EXCEPT:

Strong communicative and interpersonal skills

Familiarity with the operations of each line organization

General knowledge of the technology being used

*Understanding of various organizational structures

 

Which of the following is calculated as the initial fixed investment in the project divided by the estimated annual net cash inflows from the project?

Discounted Cash Flow

*Pay Back Period

Discounted Cash Flow

Internal Rate of Return

 

Which of the following are projects that can be accomplished by one organizational unit, say a department?

Individual projects

*Staff projects

Special projects

Matrix or Aggregate projects

 

Which of the following refers to “Design of the number and kinds of positions, along with corresponding duties and responsibilities, required to achieve or exceed objectives”?

Forecast

*Organization

Policy

Procedure

 

Which of the following refers to “a specification of series of actions, acts or operations, which have to be executed in the same manner in order to always obtain the same result in the same circumstances”?

Policy

*Procedure

Standard

Decision

 

In which of the following typical Engineering, Procurement and Construction proposal contents, conditions of request for proposal (RFP) are summarized?

*Introduction & Summary

Project Description

Scope of Services

Work Plan & Schedule

 

Which of the following involves a firm identification of the required resources along with the establishment of realistic time, cost, and performance parameters?

Conceptual Phase

*Planning Phase

Testing Phase

Implementation Phase

 

Which of the following phases can also be referred as the design phase?

Concept phase

*Acquisition phase

 

Which of the following refers to “A projection of what will happen by a certain time”?

*Forecast

Organization

Policy

Procedure

 

Which of the following is also called System Engineering?

System Implementation

System Testing

System Evaluation

*System Integration

 

Which of the following is also known as benefit to cost ratio?

Discounted Cash Flow

Pay Back Period

Future Cash Flow

*Profitability Index

 

====================================

+ How to Follow the New Added Discussions at Your Mail Address?

+ How to Join Subject Study Groups & Get Helping Material?

+ How to become Top Reputation, Angels, Intellectual, Featured Members & Moderators?

+ VU Students Reserves The Right to Delete Your Profile, If?


See Your Saved Posts Timeline

Views: 313

.

+ http://bit.ly/vucodes (Link for Assignments, GDBs & Online Quizzes Solution)

+ http://bit.ly/papersvu (Link for Past Papers, Solved MCQs, Short Notes & More)

+ Click Here to Search (Looking For something at vustudents.ning.com?)

+ Click Here To Join (Our facebook study Group)

Replies to This Discussion

Please share your quizzes as well. 

Please all students related this subject Share your online Quizzes here to help each other.thanks

 

Please share the question and their answers of this quiz if anyone has done.
Thanks. 

Quiz 2-MGMT 627-Project Management-Actual Quiz Dt.8 Dec 2015

Attachments:

RSS

Latest Activity

IBS replied to MIT's discussion Visual Programing (CS411) Assignment#01 Deadline Date = 18-11-2019 in the group CS411 Visual Programming
29 minutes ago
Ammara replied to + M.Tariq Malik's discussion MTH501 Assignment No 01 Fall 2019 Solution & Discussion Due Date: 19-11-2019 in the group MTH501 Linear Algebra
31 minutes ago
kiran ashraf replied to + M.Tariq Malik's discussion MGT611 Assignment No 01 Fall 2019 Solution & Discussion Due Date: 14-11-2019 in the group MGT611 Business & Labor Law
32 minutes ago
kiran ashraf joined + M.Tariq Malik's group
32 minutes ago
M IDREES replied to + M.Tariq Malik's discussion CS502 Fundamentals of Algorithms Assignment No 01 Fall 2019 Solution & Discussion in the group CS502 Fundamentals of Algorithms
38 minutes ago
°`·("آفروز") aFFrOzE·´° replied to + M.Tariq Malik's discussion CS401 Assignment No 01 Fall 2019 Solution & Discussion in the group CS401 Computer Architecture and Assembly Language Programming
59 minutes ago
Profile Icon°`·("آفروز") aFFrOzE·´°, Aamir Abbas and Rizwan Ali joined + M.Tariq Malik's group
59 minutes ago
M IDREES replied to + M.Tariq Malik's discussion CS502 Fundamentals of Algorithms Assignment No 01 Fall 2019 Solution & Discussion in the group CS502 Fundamentals of Algorithms
1 hour ago
M IDREES replied to + M.Tariq Malik's discussion CS502 Fundamentals of Algorithms Assignment No 01 Fall 2019 Solution & Discussion in the group CS502 Fundamentals of Algorithms
1 hour ago
Ammara commented on + M.Tariq Malik's group MTH501 Linear Algebra
1 hour ago
Ammara joined + M.Tariq Malik's group
1 hour ago
+ Haxan updated their profile
1 hour ago
+ "αяsαℓ " Ќąƶµяɨ •" posted a discussion
1 hour ago
Fojjiii updated their profile
1 hour ago
+ M.Tariq Malik replied to + M.Tariq Malik's discussion ENG101 English Comprehension Online Quiz No 01 Fall 2019 Solution Discussion Last Date: 14-11-2019 in the group ENG101 English Comprehension
2 hours ago
Aamir Abbas replied to + M.Tariq Malik's discussion CS401 Assignment No 01 Fall 2019 Solution & Discussion in the group CS401 Computer Architecture and Assembly Language Programming
2 hours ago
+ M.Tariq Malik replied to + M.Tariq Malik's discussion MGT602 Assignment No 01 Fall 2019 Solution & Discussion Due Date: 15-11-2019 in the group MGT602 Entrepreneurship
2 hours ago
+ Iuuoɔǝut + posted videos
2 hours ago
+ M.Tariq Malik is now friends with Careerz360, Sabir Hussain, Gulzar Ahmed and 11 more
2 hours ago
+ M.Tariq Malik left a comment for Muhammad Shahid Javed
2 hours ago

© 2019   Created by + M.Tariq Malik.   Powered by

Promote Us  |  Report an Issue  |  Privacy Policy  |  Terms of Service