We are here with you hands in hands to facilitate your learning & don't appreciate the idea of copying or replicating solutions. Read More>>

Looking For Something at vustudents.ning.com? Click Here to Search

www.bit.ly/vucodes

+ Link For Assignments, GDBs & Online Quizzes Solution

www.bit.ly/papersvu

+ Link For Past Papers, Solved MCQs, Short Notes & More


Dear Students! Share your Assignments / GDBs / Quizzes files as you receive in your LMS, So it can be discussed/solved timely. Add Discussion

How to Add New Discussion in Study Group ? Step By Step Guide Click Here.

ASSIGNMENT NO 1(MTH 601)

 

 

DON’T MISS THESE: Important instructions before attempting the solution of this assignment:

  • To solve this assignment, you should have good command over 1 - 9 lectures.
  • Upload assignments properly through LMS, No Assignment will be accepted        through email.
  • Write your ID on the top of your solution file.
  • Don’t use colorful back grounds in your solution files.
  • Always send your solution in dox or docx file with proper accessible math type symbols.
  • You should remember that if we found the solution files of some students are same then we will reward zero marks to all those students.
  • Also remember that you are supposed to submit your assignment in Word format any other like scan images etc will not be accepted and we will give zero marks correspond to these assignments.

 

 

 

 

 

 

 

 

 

 

 

 

Question:                                                                                            (5+5+5+5)

An engineering project consisting of the nine activities whose time estimates are given in the following table

Activities

Time estimates

1-2

1

1-3

3

1-4

2

2-5

1

3-5

3

4-6

2

5-6

4

5-7

3

6-7

6

                                                                                                  

a) Draw the Network for the project.

b) Calculate the following time estimates for each activity

  • Earliest Start Time
  • Earliest Finish time
  • Latest Start Time
  • Latest Finish Time

c) Determine Total Float, Free Float and Independent Float for each activity

d) Find the Critical path and minimum time for the completion of the project.

+ How to Follow the New Added Discussions at Your Mail Address?

+ How to Join Subject Study Groups & Get Helping Material?

+ How to become Top Reputation, Angels, Intellectual, Featured Members & Moderators?

+ VU Students Reserves The Right to Delete Your Profile, If?


See Your Saved Posts Timeline

Views: 6244

.

+ http://bit.ly/vucodes (Link for Assignments, GDBs & Online Quizzes Solution)

+ http://bit.ly/papersvu (Link for Past Papers, Solved MCQs, Short Notes & More)

+ Click Here to Search (Looking For something at vustudents.ning.com?)

+ Click Here To Join (Our facebook study Group)

Replies to This Discussion

Its Easy

any one given idea

First draw a network for this read topic 2.2 concept of network pg 9 from handouts

Please Discuss here about this assignment.Thanks
Our main purpose here discussion not just Solution
We are here with you hands in hands to facilitate your learning and do not appreciate the idea of copying or replicating solutions.

first part of question 

ap k pas ful ass ka solution h to post kr dy

yes its ryt... :)

anyone hav solution of mth601

solution post kar day koi assignment ka

Will upload the solution sonn but it better to try by urself

aj last date hai kar day abh please

i need solution mth 601

RSS

Latest Activity

© 2020   Created by + M.Tariq Malik.   Powered by

Promote Us  |  Report an Issue  |  Privacy Policy  |  Terms of Service

.