 Maximum Marks:20                                                                 Due Date: June 2, 2015

 

Question :                                                                       (Marks=10+10)

1) Calculate the following time estimates for the network given below

a) Earliest Start Time

b) Earliest Finish time

c) Latest Finish Time

d) Latest Start time

2) Find out the critical path for the given Network

imgo.jpg

+ Click Here To Join also Our facebook study Group.

..How to Join Subject Study Groups & Get Helping Material?..


See Your Saved Posts Timeline

Views: 1287

.

+ http://bit.ly/vucodes (Link for Assignments, GDBs & Online Quizzes Solution)

+ http://bit.ly/papersvu (Link for Past Papers, Solved MCQs, Short Notes & More)

Attachments:

Replies to This Discussion

Assalam O Alaikum.. Finally completed Question 1's chart for EST , EFT, LST, and LFT

hopefully it will be helpful...

Also the ctritical path is 1 -2-3-4-6-7  

Attachments:

koi to complete solution upload kr dy ab to time b ni raha itna

Dear Students Don’t wait for solution post your problems here and discuss ... after discussion a perfect solution will come in a result. So, Start it now, replies here give your 

Kaya ha sahe solution ha

Attachments:

Plz reply

koi complete solution upload kr dy